Installation – Point Drain with CPE Liner Membrane
- Where altering floor joists, consult Structural Engineer for advice and reinforce floor joists as advised.
- Frame out shower surround as required.
- Connect base of PVC CPE membrane body to pipe work, leave drain bolts in place. Block drain opening to prevent floor mortar from entering.
- Trowel mortar onto sub-floor, ensuring recommended 2% slope to drain.
- Install waterproofing membrane per manufacturer’s recommendations. Seal membrane to PVC CPE membrane body underneath,.
- Install top section of drain flange.
- Test membrane for leaks.
- Position threaded/rubber push-fit coupling in drain flange at correct position/height.
- Solvent weld point drain spigot into rubber coupling (use dish detergent to assist), at correct height and orientation.
- Trowel mortar to required height, allow for thickness of tile and thinset mortar, grade to create minimum 2% slope towards drain.
- After floor mortar has cured, apply thinset and install tile and grout.
- Install grate into body.